2026 Major Paving Operations

 In Uncategorized


The City of Atchison hired paving contractor Herzog to complete our major bond-funded mill and overlay paving operations for 2026. Herzog is in town and starting work as of October 7th, 2026. Over the next two weeks they will be completing large-scale paving operations around Atchison. Streets highlighted in red or blue on the attached maps will be the focus of their operations. Residents along these streets should receive door hangers and other notices to move vehicles when their street is next on the list. The first two streets will be Crowell and Green. Thank you for your assistance with vehicles so Herzog can complete their work as quickly as possible!

Note: these are not the only streets in Atchison being paved this year. City Street crews and other paving contractors continue working through smaller scale projects around the city as well. For the full list of targeted streets to be milled and repaved in 2026 and 2027, please reference our post from earlier this year: https://cityofatchison.com/news/city-projects/26streets/

Thank you!

 

Latest projections from the contractor for timing (depending on weather) is as follows:

Milling

L St – 10/15 (weather permitting)-Fri 10/16

Santa Fe/Parallel – Mon 10/19-Tues 10/20

S 6th St – Tues 10/20-Wed 10/21

Woodlawn – Wed 10/21-Thur 10/22

Paving

N 4th St – Thur 10/15 (weather permitting)-Fri 10/16

N 8th St – Fri 10/16-Mon 10/19

Su Terra – Fri 10/16-Mon 10/19

N 9th St – Mon 10/19-Tues 10/20

N 3rd St – Tues 10/20-Wed 10/21

Santa Fe/Parallel – Following

S 6th St – Following

Woodlawn – Following