Summary: This project will include complete reconstruction of River Road from the north boat ramps to the city limits.
Cost: About $160,000
Funding: This project is a collaboration between the City of Atchison and Atchison County. The Atchison County Road and Bridge Dept. will perform the work and the City of Atchison will pay for all of the materials needed.
Location: River Road (north boat ramp to city limits)
Contractor: Atchison County Road & Bridge
Status: Complete
Construction Start Date: April 24, 2017
Completion Date: September 28, 2017