Event Center Concrete Stairs Replacement
Summary: The north stairs at the Event Center have deteriorated to the point of becoming a safety hazard. This project will replace the existing concrete stairs.
Cost: About $32,000.
Funding: The budget for this project was originally $30,000, although bids came in higher than expected.
Location: Atchison Event Center
Contractor: BKM Construction (concrete), Bruce Gaskell Mfg., LLC (handrail)
Status: Complete
Construction Start Date: Concrete: July 2017, Handrail: Winter 2018
Completion Date: Concrete: August 2017, Handrail: Winter 2018